Final bill for Central Subway could blow budget by $130 million
"This isn’t right. ... This is not how business should be operating."
"This isn’t right. ... This is not how business should be operating."
The delayed Central Subway Project is yet again running over budget.
The San Francisco Municipal Transportation Agency Sustainable Streets Director Tom Maguire told the Board of Directors Tuesday that he anticipates the project will run over by 15 percent of the original $1.578 billion budget — the final bill is expected to add between $100 million and $130 million.
Maguire said:
“That means that the SFMTA is going to find more money to pay contract modifications, claims, and to close the project out so that we can get this thing ready for the riding public in the spring 2022 like we promised.”
Maguire added that contingency funds have already been spent.
The project, which extends the T-Third rail line into Chinatown and adds stops at new downtown stations, has been plagued by work order changes issued by the contractor, Tutor Perini.
Directors approved a first omnibus of 671 change orders from November 2013 to September 2019. After negotiations with the contractor, the agency and Tutor Perini agreed to a settlement of approximately $48 million. The agency had already paid nearly $19 million for additional costs in February.
Change orders often stem from adjustments deemed necessary for varying site conditions and design changes requested by the project sponsor. In those situations, the contractor submits an invoice to the project sponsor and cost is then assessed.
An agency staff report said the SFMTA and Tutor Perini initially failed to agree on change order charges and that Tutor Perini delayed providing documents to support its claims.
Former Public Works City Architect Edgar Lopez was hired by the SFMTA as a consultant to negotiate the current and future claims.
Director Sharon Lai expressed her frustration over the “prolific” number of change orders and the process in which they are handled, adding:
“This isn’t right. I think everybody acknowledges that, right? It’s not a secret. This is not how business should be operating.”
Referencing the contractor’s back-billing approach, she said:
“[I]t erodes the city’s ability to essentially make different financial choices had we known the cost associated with it upfront.”
Lopez told directors that two additional omnibus packages are still pending finalization, one of which includes 350 change orders issued from October 2019 to October 2020, though the final cost is still being negotiated. The other package would include change orders from November 2020 through completion of project.
Maguire indicated that the SFMTA cannot ask the federal government to fill the budget gap over the $942 million already provided as part of a full funding grant agreement. He said the agency is looking to identify new funding sources.
Transit officials last month estimated the project’s substantial completion in the spring of 2021, opening for revenue service in the spring of 2022.
Jerold serves as a reporter and San Francisco Bureau Chief for SFBay covering transportation and occasionally City Hall and the Mayor's Office in San Francisco. His work on transportation has been recognized by the San Francisco Press Club. Born and raised in San Francisco, he graduated from San Francisco State University with a degree in journalism. Jerold previously wrote for the San Francisco Public Press, a nonprofit, noncommercial news organization. When not reporting, you can find Jerold taking Muni to check out new places to eat in the city.
Police on Friday said a man who regularly filmed a child dance group based out of San Francisco’s Chinatown...
FBI officials in San Francisco are asking for the public’s help to solve an arson fire that badly damaged...
The J-Church line began rolling again Saturday, marking the first Muni rail service to return since August’s failed restart....