Crews head back into Muni’s Twin Peaks Tunnel for another round of work

The summer of 2018 was a tough time for Muni passengers and the San Francisco Municipal Transportation Agency who endured a two-month closure of the Twin Peaks Tunnel portion of the subway. Despite the lengthy project, not all work was completed as originally planned. Monday, crews headed back in for another round of construction.

During those months in 2018, train service was replaced by shuttle buses, which in turn impacted bus service elsewhere as buses and drivers were taken from other routes and used for shuttle operation. Additionally, a construction crew member died while the project was ongoing. 

Now, the transit agency will spend another possible “tens of millions” of dollars for additional infrastructure improvements and to complete work outstanding from the 2018 project.

Because the subway is already closed, the current scope of work will not affect Muni passengers. Still, transit officials were lambasted by supervisors at the Nov. 17 San Francisco Francisco County Transportation Authority commission meeting for not having completed infrastructure improvements during the 2018 tunnel closure.

One planned task the agency failed to complete in 2018 involved replacement of the track ballast — a bed of rocks that sits beneath the tracks and stabilizes the trackway. Noting track stability issues that have since emerged, Julie Kirschbaum, the SFMTA director of transit, said:

“If the ballast had been cleaned and kind of shaken out so that all of the mud and the fine particles were removed, reusing the ballast probably would have been a cost effective and time effective strategy, but it wasn’t.”

Supervisor Aaron Peskin, who chairs the SFCTA, said delays and additional issues with major transit capital projects continue to pile up, including with the Central Subway and Van Ness Improvement Project. He told transit officials:

“You’re out of excuses.”

In addition to the ballast work, crews will begin replacing overhead wire splices that in August prompted a pause in plans to fully reopen the subway. It was later found that some of the failed splices did not meet manufacturing standards — the agency has since identified a new distributor.

Supervisor Rafael Mandelman echoed Peskin’s frustration, saying: 

“It is just extraordinary that this amazing city seems unable to deliver a capital project transportation-related capital projects.”

The work beginning Monday is expected to last three months and be completed at the end of February. Related parking restrictions and lane modifications will be established near the Castro neighborhood in Mandelman’s district.

Construction is scheduled Monday through Saturday from 7:30 a.m. to 8 p.m., though hours are subject to change. Work will be suspended from Dec. 24 to New Year’s Day.

Inside the three-month span, crews will replace overhead lines, track fasteners, a switch machine and subway lights. The rails will also be ground to make for smoother and quieter rides, Kirschbaum said.

More information about the parking restrictions and traffic changes can be found on the SFMTA’s website.

Last modified November 30, 2020 2:28 pm

Jerold Chinn

Jerold serves as a reporter and San Francisco Bureau Chief for SFBay covering transportation and occasionally City Hall and the Mayor's Office in San Francisco. His work on transportation has been recognized by the San Francisco Press Club. Born and raised in San Francisco, he graduated from San Francisco State University with a degree in journalism. Jerold previously wrote for the San Francisco Public Press, a nonprofit, noncommercial news organization. When not reporting, you can find Jerold taking Muni to check out new places to eat in the city.

This website uses cookies.