Subsurface surprises slow Van Ness bus rapid transit project
San Francisco’s first bus rapid transit system along Van Ness Avenue is facing another delay.
San Francisco’s first bus rapid transit system along Van Ness Avenue is facing another delay.
San Francisco’s first bus rapid transit system is facing another delay.
The project is currently undergoing utility work, which includes the replacement of the water main, installing twin sewers, and replacing parts of the emergency water system to fight fires along Van Ness Avenue.
Crews digging under the concrete are finding old and abandoned utilities that were not known to the San Francisco Municipal Transportation Agency, said Peter Gabancho, SFMTA project manager for the Van Ness Improvement Project:
“The extent of utility conflicts we are finding is unfortunately increasing the days necessary to complete this phase of the construction.”
Gabancho told the San Francisco County Transportation Authority board Tuesday that, because of the new discoveries, the project is now slated open in late 2020.
He said there were underground utilities that the transit agency knew about through surveying the area and using maps, but discovering additional infrastructure was a surprise for crews.
For instance, workers found the remains of an abandoned retaining wall used for the original construction of a building along Van Ness Avenue.
The transit agency had to make sure the wall was still not in use, identify who owned it if possible, and determine how to work around the wall, said Gabancho.
Crews are testing ground-penetrating radar to find abandoned utilities as work continues, and will need to make sure they can safely remove items that are discovered. Gabancho said it takes time in removing the abandoned infrastructure.
SFMTA spokesperson Paul Rose said it was possible for crews to continue to find abandoned utilities as utility work continues.
Another issue arising is claims made by the main contractor Walsh Construction. The contractor filed eight potential claims but were all rejected by the SFMTA.
Three claims, though, have materialized, totaling approximately $21.6 million, said Gabancho.
During an update of the project in October last year, Gabancho told the board that the contractor believes it is The City’s fault for the lack of competitive bids when they put out a bid out for subcontractors.
Jerold serves as a reporter and San Francisco Bureau Chief for SFBay covering transportation and occasionally City Hall and the Mayor's Office in San Francisco. His work on transportation has been recognized by the San Francisco Press Club. Born and raised in San Francisco, he graduated from San Francisco State University with a degree in journalism. Jerold previously wrote for the San Francisco Public Press, a nonprofit, noncommercial news organization. When not reporting, you can find Jerold taking Muni to check out new places to eat in the city.
San Francisco-owned public parking garages are seeing in fewer car break-ins thanks to improvements being made inside the garages.
A BART extension to two new stations in Pittsburg and Antioch will debut with a ribbon-cutting ceremony and free...
Tetra Tech, a firm contracted by the U.S. Navy to clean up radiation at San Francisco's Hunters Point Shipyard,...